Larks Green

Enso Energy, through its subsidiary company Iron Acton Green Limited, is proposing to develop a solar farm and battery storage facility on land north and west of Iron Acton substation, BS37 9TX.

Projects  > Larks Green

Introducing Larks Green

It is estimated that the solar farm will generate approximately 60,000MWh of clean renewable electricity per year for distribution to the national grid. This is equivalent to the annual electrical needs of approximately 16,000 family homes. The anticipated CO2 displacement is around 15,000 tonnes per annum, which represents an emission saving equivalent of a reduction in 7,000 cars on the road every year.

The battery storage system will supply electricity to the local electricity network at times of peak energy demand and help make the renewable energy output of the solar farm a secure and reliable part of the UK energy supply.

16,000

homes powered per year (equivalent)

60,000

MWh of clean electricity produced per year

Consultation

We held an online public consultation webinar and Q&A session event on 3rd July 2020. The webinar included a ten-minute presentation by the project team where they outlined the draft proposals. During the Q&A session which followed the webinar attendees had the opportunity to ask questions about the draft proposals – the webinar is available to watch by clicking the video below.

Where is Larks Green Solar Farm

Larks Green Solar Farm concept design

What are the features and benefits of the solar farm and battery storage facility?

The main benefits of the development proposed are summarised below:

  • It will assist South Gloucestershire Council to reduce greenhouse gas emissions in line with local, national and international targets and its declared Climate Emergency.
  • Contribute towards the security of energy supply in South Gloucestershire Council through the provision of local, competitive renewable energy supply.
  • The management of the Ladden Brook will be repurposed toward nature with new planting and habitat creation, with the proposed permissive footpath leading to a new ecology and renewable energy interpretation area, allowing the local community to learn first-hand about climate change, renewable energy and the natural environment.
  • The proposed Lower Farm Green Corridor will provide an important ecological and landscape feature forming a continuous 1.5km green spine to the proposed Ladden Brook Nature Area, with substantial new planting improving biodiversity, ecological connectivity and also the amenity of the public footpath that runs along it.
  • A solar plant allows agricultural land to rest for the period of operation and the land use can easily be reversed to agriculture at the end of the project life.
  • No protected landscape, heritage or ecological designations will be affected by the solar farm.
  • The proposed development’s panels will utilise bifacial modules which absorb irradiation from the front and rear side, generating c. 4% higher energy yield than mono-facial modules.
  • We anticipate that construction will be complete in approximately 7 months. This will typically require up to 8 deliveries each day during peak construction.
  • Enso Energy is committed to using local suppliers during construction and operation where possible.
Sketch view from the Ladden Brook Nature Area
Sketch view from the footpath within the Lower Farm Green Corridor

Getting to net zero

The UK Government has signed up to a Renewable Energy Directive to provide 15 per cent of energy from renewables by 2020 (based on a 2008 baseline). In addition to this, the Government has made a legal commitment to cutting carbon emissions to net zero by 2050 (Climate Change Act 2008 (2050 Target Amendment) Order 2019). To achieve net zero by 2050 will require a rapid and expanded deployment of low carbon power, including solar. In July 2019 South Gloucestershire Council joined a growing number of local authorities who have declared a climate emergency. South Gloucestershire Council has pledged to enable South Gloucestershire to become carbon neutral by 2030 and is also signing up to the UK100 pledge to ensure 100% renewable energy across the area by 2050.

Our vision

At Enso Energy we are making the idea of a country run on renewable energy a reality. We are one of the UK’s most experienced energy developers and we’re headquartered locally in Dursley. Our ambition is to use the latest solar technology to make a positive impact on our country and the communities we work with. We are firm advocates for renewable, low carbon, efficient, secure and sustainable energy that can be generated, stored and utilised locally. We are passionate about creating positive change for the UK’s energy requirements and carbon commitments. Our innovative and entrepreneurial approach to subsidy-free renewable energy is assisting the country’s move towards a more secure renewable energy supply and accelerating

Our approach to consultation during the Coronavirus crisis

We are currently living through a pandemic, the likes of which the country has not experienced in living memory. Enso Energy agree with the recent guidance issued by the UK Government’s Chief Planner, which emphasised that planning applications that positively impact the country and local communities must continue to come forward.

Enso Energy believes that it is vital that local communities are able see and shape planning applications that may have an impact on them.

We therefore held a public consultation webinar and Q&A session, a recording of which can be viewed here. If you have any feedback on our draft proposals please fill in the form below.

Register for updates

If you would like to be kept up to date with Enso Energy’s plans for Larks Green Solar Farm then please contact Alpaca Communications via the form below or contact Jasmine, a member of the project team. Please view Alpaca Communications’ privacy policy here.

t: 020 7499 2842
e: jasmine.el-gabban@alpacacommunications.com

Please provide your contact details if you wish to get a response. Any information provided will only be used for the purpose of the planning application to the Local Planning Authority and will not be disclosed with any third parties. Your contact details will not be listed on the planning application documentation.


local residentlocal businessrepresentative of a local group or organisation

Solar field